Skip to main content

Sandy Ground Bridge: is the boating industry being sacrificed?

Par Ann Bouard
17 November 2026

With the Sandy Ground Bridge having been closed for over 90 days, maritime professionals have been taking action since 5 November, putting up banners as a sign of their discontent. On Friday 13 November, just before the Territorial Council meeting, they requested a meeting with the President of the Collectivité. At stake is the survival of their businesses.

As a reminder, the Sandy Ground Bridge has been completely closed since 11 August (see our 6 November edition). The findings of the fault assessment and a reverse schedule for the works were due to be provided to Métimer on 15 October… Last Friday, on the day of the Territorial Council meeting, they pressed hard to secure a meeting with the President and his staff in order to obtain this technical assessment, the names of the contractors commissioned, details of the planned works and the reasons why nothing has been undertaken since August. They also criticise the lack of dialogue with the Collectivité.

Businesses under threat and jobs hanging in the balance

The situation is already having an impact on the entire nautical sector (direct financial losses for businesses, activities gradually shifting to the Dutch side…) but also on the Collectivité, with a loss of tax revenue. Ultimately, the situation could lead to half of the companies closing down by the end of the season.
They also emphasise that the bridge forms part of the Marina Royale’s public service delegation (DSP) and that without it, it will be very difficult to attract investors. It therefore risks being postponed yet again, whilst negotiations with the two prospective candidates are under way (the candidates in question are yet another matter!) and are expected to be concluded within a few weeks.
Whilst they do not dispute the existence of technical or regulatory constraints, the industry representatives are asking the Collectivité to first explore the possibility of repairing the bridge so that it can be used even just once a week, even in a reduced capacity, and to use an emergency procedure for all the repairs, citing the fact that we are still in the cyclone season until the end of the month… but 15 days to speed things up seems futile and the announced timetable is perplexing.

April 2027: a wasted season

Isabelle Gorizia, Deputy Director-General for the Living Environment, has ruled out any possibility of the bridge being opened on an ad hoc basis. The risk of it becoming stuck in the open position would be too great. The recent jamming incidents and fires have damaged the hydraulic system and the automated controls, and the condition of the deck also requires major structural work.
The refurbishment will involve repairing the hydraulic system, bringing the guardrails up to standard, replacing the door to the plant room, and replacing the filters, electrical conduits and barriers, before tests can be carried out on the motors, cylinders and sensors… The assessment was carried out by an external consultancy, which is also responsible for consulting with contractors and supervising the works.
The schedule allows for a two-month preparation and procurement period (the equipment is not available on the island), starting from the moment the contractor is appointed… meaning work is set to begin on 12 April 2027!  The duration of the works is then estimated at 15 days.
Why was the contract not put out to tender earlier? When was the assessment carried out? These are all questions that remain unanswered. A further meeting is scheduled for 19 November, during which the new regulations being considered by Anguilla will also be discussed. In particular, Métimer is calling for the introduction of a low-cost annual ‘Cruising Permit’ for recreational boaters whose vessels are registered in Saint Martin or Saint Barthélemy. 

Ann Bouard